Structure Your Dream Home-- Part 3
Outside Framing Continues
With the homes sub-floor down and the exterior walls framed and up, the framing crew was on to the roofing. Though the roofing system was rather simple in structure with simply a 12/12 pitch and no valleys it was a substantial framing undertaking due to just the size and height of it. The house was 32 feet wide by 44 feet in length, and the exterior side walls stood 11 feet high in the excellent space. This outside wall height of 11 feet translated into a roofing check out this read ridge that was 27 feet off the floor of the great space. As a result staging was required to install the ridge pole and roofing rafters. In addition, because the period from the top of the walls to the ridge was so long, heavy 2x12s were required for the roofing rafters. Within a week, nevertheless, the group had completed the installation of the roofing rafters and your house started to handle genuine shape.
I should comment briefly about the sub-floor and exterior walls before I move on.
I chose using tongue and groove plywood for the sub-flooring instead of OSB/particle board as I was worried that the OSB was too sensitive to wetness. I was worried about this, both from the building and construction stage and from typical home usage. I was concerned that during the building and construction phase that snow and ice could potentially result in harm such as warping. I have seen this before when OSB was utilized on sub-flooring. I was also worried that during the life of the home, that there might be water occurrences, e.g. a dripping dishwashing machine or washer device that likewise could also lead to water damage to the floor. I also think that plywood is more powerful and that it would attend to a more strong and stiff floor.
Regarding the outside wall framing I utilized 2 × 6 building and construction. This is typical in New England as the additional wall depth enables greater insulation factors; a must in colder climates.
Sheathing the Beyond the Home
In order to get plumbing and electric contractors onto a site usually they desire the home buttoned up. This includes the roofing shingled and the doors and windows on. Therefore my framing team moved onto the exterior sheathing once the walls and roof framing were complete.
As with the sub-floor, I once again picked plywood for the exterior sheathing for the very same factors discussed earlier. On the exterior walls exterior grade plywood was used. On the roofing system 5/8 outside grade plywood was used. I know many home builders today use OSB for both the walls and roof, nevertheless, I still believe for stronger building and construction plywood is the way to go.
The sheathing effort took about a week to complete. Throughout this time outside doors and windows appeared on the site. Staging the delivery of material reduces theft and insurance threat as well as keeps a less chaotic building and construction website. However, as I have indicated previously, communication is important when you are doing Just-in-Time product delivery.
Installing Outside Doors and Windows
The installation of the doors and windows was a significant endeavor for this task as the lake side view of the home was actually a wall of windows; 32 feet in width and 27 feet in height. A good deal of engineering had actually gone into the window style so that the 10 large custom-made windows would fit together like a jig saw puzzle. This said, when the windows got here on site and were inspected, it was figured out that a few of them were not developed correctly to the measurements specified. After much dispute with the framing team, the window supplier and me we reached a compromise on sharing the cost of fixing the windows. The window supplier reclaimed the improperly sized windows and the framing team started the setup of the doors and what windows they might set up. Thankfully the window supplier had the ability to go back to the site with the properly sized windows within a couple of days and the building phase did not miss a beat.
Completing the Interior Framing
With the doors and windows set up, the framing team continued to finish the Interior Framing. This was an interesting time, as the spaces began to take real shape. You might now walk down corridors and into bedrooms and closet locations. Within simply a couple of days the interior walls were total and the framing team proceeded onto the roof for the shingling.
I should note that 2 × 4 building and construction was utilized on the interior walls as insulation was not needed on the interior walls.
Shingling the Roof
The last job to complete before your home might be categorized as Buttoned Up was to set up the shingles on the roofing system. Fortunately my framing team was likewise able to do this job, therefore getting rid of the requirement for yet another subcontractor.
I picked a thirty years architectural shingle due to the quality and look I was attempting to achieve on the home.
Though reasonably an easy roofing, it was rather big and the weather condition was less than congenial. Subsequently it took nearly 2 weeks to complete this task. However, with the roof total, my electrical and pipes professionals were now able to start their work.
Also, with the primary house now structurally complete, the framing crew moved onto the garage framing and construction phase. As a result of staging the garage behind the main home construction phase, I was able to have subcontractors work in parallel without getting in each others way.
Rough Electric and Plumbing
With the house Buttoned-Up, my Electric and Plumbing subcontractors showed up to begin the roughing in phase of their respective tasks.

I had met a couple of days before on site with the Electric subcontractor to talk about the positioning of all the wall outlets and switches, along with where the lighting fixtures would be positioned. Throughout our conversation he marked the wall studs for the placements of the electric wiring boxes so that we might envision the entire electrical wiring plan. We also marked where the telephone and cable boxes would reside.
During the electrical rough in circuitry phase, the electrical expert set up all the wiring boxes and ran wire from packages to where the main circuit panel box would reside.
Rough Plumbing
As with the Electrical Subcontractor, I had actually satisfied numerous weeks previously with the Plumbing Professional. During this meeting we went over the form of heat for the home, in addition to where the bathrooms and cooking area were to live in the home. We also talked about kinds of bathroom fixtures consisting of tubs, sinks and toilets. Subsequently, when he appeared on site he brand-new precisely where to run main drain and supply pipelines and vent stacks. He also roughed in all of the plumbing for each restroom and cooking area plumbing fixture.
Within a week both the Electrical and Rough Pipes specialists had actually finished their jobs and had actually effectively passed their particular evaluations.